Data Submission timelines for CY2025 - written / infographic / worksheet formats
Resubmission
Important Notes:
ORYX Performance Measurement Reporting via the DDSP is required; reporting was optional prior to CY2024.
Chart-abstracted data is due quarterly (3 months after the end of the quarter), reporting monthly, aggregate data points for each quarter.
Existing organizations that did not submit data prior to CY2025 need to accept their DDSP invitation and complete the onboarding process in order to enter data for CY2025. Contact hcooryx@jointcommission.org to request the invitation be resent.
Open/close dates and deadlines are shown within the platform
To be considered for an exemption from submitting chart-abstracted data requirements, organizations must complete and submit an extenuating circumstance request; all forms must be received at The Joint Commission no later than thirty (30) days prior to quarter close applicable to the request.
See 2. General ORYX Information--Basics Q2.8 and Q2.9 for more information on Extenuating Circumstance Requests (ECRs).
Feedback on submitted chart-abstracted data is posted to Organization’s Accelerate PI Dashboard in their Joint Commission Connect site approximately three months after the submission deadline.
Data Submission timeline for CY2025 CAM data
CY2024 Chart-Abstracted Measures (CAM)
1Q 2025 (Jan, Feb, Mar): DDSP opens February 1, 2025 and data must be entered by June 30, 2025
2Q 2025 (Apr, May, Jun): DDSP opens May 1, 2025 and data must be entered by September 30, 2025
3Q 2025 (Jul, Aug, Sep): DDSP opens August 1, 2025 and data must be entered by December 31, 2025
4Q 2025 (Oct, Nov, Dec): DDSP opens November 1, 2025 and data must be entered by March 31, 2026
Data Submission timelines for CY2025 - Infographic
CY2025 Worksheet for Data Submission
Key Dates | Type | Task |
---|---|---|
Anytime |
| Invite Additional Users (such as Quality, Data Analyst, Informatics, IT, vendor/consultant) to the DDSP (if applicable/necessary). More than one Site Administrator is recommended. |
02/01/2025 | CAM | DDSP OPENS for 1Q2025 chart-abstracted entry |
05/01/2025 | CAM | DDSP OPENS for 2Q2025 chart-abstracted entry |
06/30/2025 | CAM | DDSP DEADLINE 11:59 p.m. Central Time for 1Q2025 chart-abstracted entry |
08/01/2025 | CAM | DDSP OPENS for 3Q2025 chart-abstracted entry |
09/30/2025 | CAM | DDSP DEADLINE 11:59 p.m. Central Time for 2Q2025 chart-abstracted entry |
11/01/2025 | CAM | DDSP OPENS for 4Q2025 chart-abstracted entry |
12/31/2025 | CAM | DDSP DEADLINE 11:59 p.m. Central Time for 3Q2025 chart-abstracted entry |
03/31/2026 | CAM | DDSP DEADLINE 11:59 p.m. Central Time for 4Q2025 chart-abstracted entry |