The Joint Commission

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 7 Next »

Topics Covered in this section:

  • Verifying ORYX Requirements via HCO Characteristics

  • Chart-abstracted data - verifying data is submitted and Submission Report

  • eCQM data - verifying data is submitted and Submission Report


Verifying ORYX Requirements via HCO Characteristics

  1. ORYX Requirements are determined by organization type, service, and volume

  • HCO Characteristics references information from organization's Joint Commission Connect site > General Application to determine ORYX requirements.

  • To view how your organizational requirements are categorized on the DDSP, select “HCO Characteristics” from the menu.

Screenshot of the DDSP home page screen, highlighting HCO Characteristics in the Table of Contents

2. Verify your program and organization type to determine your ORYX requirements

  • If the information on the DDSP needs to be updated, submit a support ticket via the “Need Help?” button

Screenshot of the HCO Characteristics screen highlighting the Organization Requirements tab with an arrow specifying the (HAP) Hospital Type

3. There are currently 3 programs (ALC, CAH, HAP) and 3 sub types of HAP1 (Large, Small, Psych) with ORYX requirements:

A screenshot of the Program types and Hospital types, including  Programs for Assisted Living Facility, Critical Access Hospital, and HAP Hospital Accreditation Program, with HAP subsets of HAP Small, HAP Large, and HAP Freestanding Psych as outlined in the ORYX requirements.

1 Organizations can have multiple program types, e.g., both HAP and CAH
2 HAP Large requirements are further determined by obstetrical services

4. ORYX requirements are posted on the external Joint Commission website under both “Reporting” and “Resources”:

Screenshot of the Measurement section of the external Joint Commission website, with arrows pointing to the Reporting and Resources section where users can find Annual ORYX Requirements.

5. Use the information (updated annually) to determine what the annual requirements & available measures are for your organization

NOTE: the screenshot below is for example only and should not be used to determine requirements for your organization.

Screenshot example of an annual ORYX Performance Measurement Requirements document

Chart-abstracted data: verifying data is entered & Submission Report

For additional information on chart-abstracted data submission, refer to the Chart-abstracted measures Help/Confluence contents: https://jointcommission-ddsp.atlassian.net/wiki/spaces/DCS/pages/19464193

6. For those organizations with specific required measures, those measures will be indicated in blue italic text as: (Required)”.

  • If an organization submits an optional measure for the first calendar quarter, that measure becomes required for the full calendar year; organizations may not stop/start measures mid-year with the exception of unit closures (i.e. closure of an obstetrical unit).

  • When chart-abstracted data is submitted, the measure will show as “Complete”.

  • When chart-abstracted data is entered for some months of a quarter, the measure will show as “In Progress”.

  • When a chart-abstracted data is not entered for a required measure, it will show as “Not Started”.

  • Any measure showing as “Not started” or “In Progress” is not submitted and the requirement is not met.

A screenshot of the chart-abstracted measure submission page indicating measures as Complete, In Progress, or Not Submitted.

7. The Home Page Chart-abstracted Submission status:

a) Indicates the status of the currently displayed HCO.

b) The status for all HCOs the user has access to is displayed when selecting “Open” from the home page chart-abstracted measure submission status section.

c) The Chart-abstracted measure Submission report for each HCO the user has access to should be downloaded by selecting the text, “Download Submission Report”.

Screenshot image of the DDSP home page indicating Chart-abstracted status of complete, and the Open button to download the submission report for the active HCO.

8. The Home Page Submission status for HCOs not submitting Chart-Abstracted Measures

  • Chart Abstracted Status 1Q(Year) Not Started – if an organization is not required or electing to submit optional chart-abstracted measures, or are submitting eCQMs to meet their ORYX requirements, this status can be ignored.

Screenshot of the DDSP Homepage indicating a Chart-abstracted status of 1Q(Year) Not started

Don’t enter zeros for measures you’re not submitting data for; only enter data for measures your organization is required and/or electing to submit.

If your organization does not provide obstetrical services, do not enter zeros for the PC measures.

EXCEPTION: If your OB unit closed mid-quarter, do enter zeros to complete the quarter and all quarters remaining for the calendar year

9. The Joint Commission’s DDSP Support Staff and HCO ORYX email staff are not able to individually verify submission status.

  • All organizations, including those using a vendor / or consultant, are responsible for verifying their data is submitted on time, correctly, and as expected prior to established deadlines.

  • Users with access to the DDSP should download the submission report from the DDSP homepage as verification / proof of submission and verify the report reflects the data submitted.

eCQM data: verifying data is submitted & Submission Report

For additional information on eCQM data submission, refer to the eCQMs Help/Confluence contents: https://jointcommission-ddsp.atlassian.net/wiki/spaces/DCS/pages/24936467

10. Upload, Validate, Verify eCQM Data prior to submission.

  • Upload QRDA data for the applicable year via the eCQM Upload Data page and verify the upload by checking the Upload Summary tab

  • After receiving the upload success message on the upload page, it might take up to 48 hours to see the results in Data Accuracy and the Quality Improvement (QI) page

  • Set the notification in User Settings to be notified when your uploaded data has processed and is ready for review.

Screenshot of the DDSP homepage eCQM Submission Table of contents and User Settings.

11. eCQM Data Submission; upload and review your data and verify the measure outcomes prior to data submission. When ready to submit:

a) Select each quarter you plan to submit

b) Select each measures you intend to submit

c) Select an attestation box if applicable

Then scroll to the bottom of the page and select “Submit” and Confirm Submission.

Screenshot of the eCQM submission page indicating the Select Quarter toggle, submit check box, and threshold exemption check box.

d) When you submit data, attestation boxes are validated

e) You will be provided a description of ORYX requirements for your Facility to ensure you are meeting the requirements

f) You can submit data and withdraw the submitted data until the deadline to correct any data issues.

Screenshot of the DDSP eCQM submission pop up message to verify submission, including ORYX Policy, with buttons to confirm or cancel submission.

12. eCQM Submission Report

  • After data has been submitted, a banner indicating that data has been successfully submitted will remain at the top of the eCQM submission page.

  • Users should download the submission report at the bottom of the page as proof of submission

  • Verify the report reflects the data submitted

Screenshot of the DDSP eCQM submission page banner indicating eCQM data has been successfully submitted. An additional highlighted snapshot from the bottom of the submission page shows the options to withdraw the submission or download the submission report.

13. Home Page eCQM Submission status should indicate “Submitted” and the Submission Report is available to download.

a) Indicates the status of the currently displayed HCO.

b) The status for all HCOs the user has access to is displayed when selecting “Open” from the home page eCQM measure submission status section.

c) The eCQM measure Submission report for each HCO the user has access to should be downloaded by selecting the text, “Download Submission Report”.

Screenshot of the DDSP homepage indicating the eCQM status as Submitted and the Open button to download the submission report for the active HCO.


End of Topic Section

  • No labels